Akash can do a piece of work in 4 days and Dhruv can do the same work in 6 days. If they both work together , how much time will they take to complete the work?
Answers
Answered by
1
Step-by-step explanation:
work done by Akash in 1 day = 1/4
work done by Dhruv in 1 day = 1/6
work done by both in 1 day = 1/4 + 1/6
3+2/12 = 5/12
They can finish the work in(1÷5/12)2days6hours