Math, asked by meero5738, 8 months ago

Ali completes 5/8 of a job in 20 days.How many more days will he take to finish the job at his current rate

Answers

Answered by sarveshm007
0

Answer:

12 DAYS

Step-by-step explanation:

5/8 OF A JOB IN 20 DAYS

1/8 OF A JOB IN 4 DAYS

REMAINING JOB = 8/8 - 5/8 =3/8 = 12 DAYS

HENCE HE WILL TAKE 12 DAYS TO COMPLETE THE JOB

HOPE IT HELPS YOU

Similar questions