Aman can do a piece of work in 15 days and Rohan alone can do it in 10 days. Rohan works at it for
5 days and then leaves. In how many days Aman alone can finish the remaining work?
no worng answers or I will report it
Answers
Answered by
1
1/x=1/15,x=15.
1/y=1/10,y=10.
m be the required days for aman to complete the remaining eork.
5/10+m/15=1.
m/15=1/2.
m=15/2days or 7.5days.
Therefore,the answer is 7.5days or 15/2 days.