amit can do a piece of work in 6 days and bina can do it for 12 days . how long will they take work together .
Answers
Answered by
2
ANSWER:4
STEP- BY -STEP EXPLANATION:
Amit can do a piece of work in 6days
One day work of Amit=1/6
Bina can do a piece of work in 12days
One day work of Bina=1/12
In how many days can they complete the work together?
1/6+1/12
=2+1/12
=3/12=1/4
One day work of both Amit and Bina together=1/4
So,They they both can complete the work together in 4days.
Hence, your required answer is 4.