Math, asked by rahulnathan588, 3 months ago

An amount of work can be completed by 24 men working 8 hours a day in 10 days. How many men
with the same efficiency are required to complete the same work in 6 days, working 10 hours a day?​

Answers

Answered by Abgail
24

Step-by-step explanation:

here's ur answer!!

thanks!!

Attachments:
Answered by marishthangaraj
2

Given:

An amount of work can be completed by 24 men working 8 hours a day in 10 days.

To find:

The number of men required to complete the same work in 6 days by working 10 hours a day.

Solution:

An amount of work can be completed by 24 men working 8 hours a day in 10 days.

Therefore,

Total number of hours taken by 24 men to complete the work is,

24 × 10 × 8

Total number of hours taken by 24 men to complete the work = 1920 hours

The number of men required to complete the same work in 6 days by working 10 hours a day is 'x'

x × 10 × 6 = 1920

x = \frac{1920}{60}

x = 32

Therefore,

The number of men required to complete the same work in 6 days by working 10 hours a day is 32

Final answer:

32 men with the same efficiency are required to complete the same work in 6 days, working 10 hours a day.

Similar questions