An amount of work can be completed by 24 men working 8 hours a day in 10 days. How many men
with the same efficiency are required to complete the same work in 6 days, working 10 hours a day?
Answers
Step-by-step explanation:
here's ur answer!!
thanks!!
Given:
An amount of work can be completed by 24 men working 8 hours a day in 10 days.
To find:
The number of men required to complete the same work in 6 days by working 10 hours a day.
Solution:
An amount of work can be completed by 24 men working 8 hours a day in 10 days.
Therefore,
Total number of hours taken by 24 men to complete the work is,
24 × 10 × 8
Total number of hours taken by 24 men to complete the work = 1920 hours
The number of men required to complete the same work in 6 days by working 10 hours a day is 'x'
x × 10 × 6 = 1920
x =
x = 32
Therefore,
The number of men required to complete the same work in 6 days by working 10 hours a day is 32
Final answer:
32 men with the same efficiency are required to complete the same work in 6 days, working 10 hours a day.