Math, asked by sidthart, 1 year ago

an engineer had a work force of 260 persons, under took to complete a work in 10 months. He was asked to complete the work in 2 months. how many extra persons be needed to finish the work in months?​

Answers

Answered by sahilgupta19
3

Step-by-step explanation:

1300 Persons are needed to finish the work in 2 months

Answered by haridasan85
9

Step-by-step explanation:

MEN PERIOD

260. 10mos

x. 2mos

x=10x260/2=1300

Total 1300 men

EXTRAMEN=1300-260=1040