an engineer had a work force of 260 persons, under took to complete a work in 10 months. He was asked to complete the work in 2 months. how many extra persons be needed to finish the work in months?
Answers
Answered by
3
Step-by-step explanation:
1300 Persons are needed to finish the work in 2 months
Answered by
9
Step-by-step explanation:
MEN PERIOD
260. 10mos
x. 2mos
x=10x260/2=1300
Total 1300 men
EXTRAMEN=1300-260=1040