an engineer had a work force of 260 persons, under took to complete a work in 10 months. He was asked to complete the work in 2 months. how many extra persons be needed to finish the work in months?​

Answers

Answered by dakshhalai
1

Answer:

52

Step-by-step explanation:

260 person need 10Months

?? need 2Months

260×2÷10

520÷10

=52