An engineer undertakes a project to build a road 15 km long in 300 days and employs 45 men for the purpose. after 100 days, he finds only 2.5 km of the road has been completed. find the (approx.) number of extra men he must employ to finish the work in time.

Answers

Answered by sanjivkumar717p721mf
6
112.5-45 = 67.5men
so minimum 68 men additional needed.
Attachments:
Answered by KingNipunop
6

If you like my answer please mark me as brainliest