and B together can do a piece of work in 6 days and B alone can do the work in 9 days in how many days will be alone finish the work
Answers
Answered by
3
Answer:
18 days
Step-by-step explanation:
Since, a alone do the work in 9 days,
So, the one day work of A =
Also, both a and b do the work in 6 days,
⇒ The combined one day work of a and b =
Thus, the one day work of b = The one day work of both a and b - One day work of a
Hence, the time taken by b alone =
Answered by
3
Answer:
18
will be our answer
A+B=1/6
B=1/9
A=A+B-B=1/6-1/9
1/18
A complete the work in 18 days