anil will take 10 days to dig a well sunil will take 15 days to dig a same well. In how many days they be able to dig a well if they work together
Answers
Answer:
6 days
Step-by-step explanation:
Anil=1/10
Sunil=1/15
both together =1/10+1/15=
3+2/30
5/30
days =1/1/30=30/5
6 days
It will take 6 days to dig a well if they work together.
Explanation:
Rate of work
Given : Anil will take 10 days to dig a well.
We count the whole work as 1.
Rate of work for Anil =
Sunil will take 15 days to dig a same well.
Rate of work for Sunil =
let t be the time they will take to dig well if they work together.
then According to the question, we have
Hence, it will take 6 days to dig a well if they work together.