Ankur can finish a work in 4 days and Varun can finish the same work in 8 days . Find the number of days required by Ankur and Varun to finish the work, if they work together.

Answers

Answered by preetitiwari7233
1

Answer:

Question

ankur can finish a work in 4 days and varun can finish the same work in 8 days. find the number of days required by ankur and varun to finish the work, if they work together