5. If 12 men can do a piece of work in 45 days. In how many days will 27 men do it?
(a) 10 days
(b) 15 days
(c) 20 days
(d) None of these
Ans. :-
Answers
Answered by
0
the answer is non of these ok
Answered by
0
Answer:
20 days is the answer
Step-by-step explanation:
12 men work 45 days, that is 12 × 45 = 540 days to complete the task.
If we have 27 men available, and assume the same work, they will also need 540 days. But as they are more, the time needed will be 540/27 = 20 days.
So, it takes 20 days for 27 men to do the same work.