Answers 2 no question fast
Attachments:
Answers
Answered by
1
Step-by-step explanation:
10 workers
mark me as brainliest
Answered by
0
Answer:
total work 7×20=140
worker need= 140÷14=10
Similar questions
Math,
2 months ago
English,
5 months ago
CBSE BOARD XII,
5 months ago
Social Sciences,
10 months ago
Math,
10 months ago
Science,
10 months ago