Anuj and Bhanu can together finish a work in 30 days. They worked together for 20 days and then Bhanu left. After another 20 days, Anuj finished the remaining work. In how many days Anuj alone can finish the job?
Answers
Answered by
2
Anuj & Bhanu finish the work in 30days.
In 20 days they have finished 20/30= 2/3 of work
The work left was 1-2/3=1/3
Anuj finished the work 1/3 work in 20 days
Anuj would finish the whole work in 1*20/(1/3)=60 days.
Alone Anuj would finished the work in 60days.
In 20 days they have finished 20/30= 2/3 of work
The work left was 1-2/3=1/3
Anuj finished the work 1/3 work in 20 days
Anuj would finish the whole work in 1*20/(1/3)=60 days.
Alone Anuj would finished the work in 60days.
gautamisahoo:
please mark as best
Answered by
1
60 days
A+B=1/30 of the work in one day
In one day 20(1/30) of the work completed. Therefore 1/3 of work left
It takes 20 days ( anuj ) to complete 1/3 of work
Therefore work done in one day (1/3)/20=1/60
Therefore he will complete the work in 60 days alone