Math, asked by Luckshitha, 9 months ago

anyone ans me
very needed​

Attachments:

Answers

Answered by schahat256
1

Let a,b & c be the number of days taken by A, B & C to complete the work alone.

Given, A can do a piece of work in four hours.

=> 1/a = 1/4——————(1)

B and C together can do it in 3 hours,

=> 1/b + 1/c = 1/3———-(2)

A and C together can do it in 2 hours,

=> 1/a + 1/c = 1/2———-(3)

Using (1) & (3)

1/c = 1/2 - 1/4 = 1/4——-(4)

Using (2) & (4)

1/b = 1/3 - 1/4 = 1/12

=> b = 12

=> The number of days taken by B to complete the work alone is 12 hours

Answered by Anonymous
2

Answer:

the answer is 12

Step-by-step explanation:

please mark as brainlist