Math, asked by amanrastogi7540, 9 months ago

Arrangement of tables and chairs in an exam hall done by 10 workers in 6 hours? Howmany workers will be required to do the same work in 4hrs?​

Answers

Answered by krishtys
8

Answer:

15

Step-by-step explanation:

given, 10 workers can do a work in 6 hours.

let the no. of men required be x

it is a case of inverse variation.

so we have,

10*6=x*4

x=(10*6)/4

x=15

so 15 workers will be required to do the same work in 4 hours.

Answered by malekkulsum254
3

Answer:15

10 workers for 6 hours,

Then how many workers for 4 hours?

So 6×10÷4= 15

So answer is 15 by me

Similar questions