Arun , Bharath, Karthik can
complete a work separately in
24, 36 and 48 days. They started
working together but Karthik left
after 4 days of start and Arun left
3 days before completion of the
work. In how many days will the
work be completed?
Answers
Answered by
20
Explanation:
Arun , Bharath, Karthik can complete
a work separately in 24, 36 and 48
days. They started working together
but Karthik left after 4 days of start
and Arun left 3 days before
completion of the work. In how many
days will the work be completed?