Arun , Bharath, Karthik can complete
a work separately in 24, 36 and 48
days. They started working together
but Karthik left after 4 days of start
and Arun left 3 days before
completion of the work. In how many
days will the work be completed?
Answers
Answer:
Arun 28 Bharat 39
Explanation:
Arun 24+4=28
Bharat 36+3=39
The number of days taken to complete the total work = 12 3/5 days
Given:
Arun, Bharath, Karthik can complete a work in 24, 36 and 48 days. respectively
They started working together but Karthik left after 4 days of start and Arun left 3 days before completion of the work
To find:
In how many days will the work be completed?
Solution:
Given Arun can complete a work in 24 days
⇒ The work can be done by Arun in 1 day = 1/24
Bharath can complete a work in 36 days
⇒ The work can be done by Bharath in 1 day = 1/36
Karthik can complete a work in 48 days
⇒ The work can be done by Karthik in 1 day = 1/48
They started working together, and worked for 4 days
The done in 4 days =
= =
=
Karthik left after 4 days of start,
Let's assume that after leaving Karthik,
Arun and Bharath worked for x days,
then work can be done by Arun and Bharath in x days
= =
=
Arun left 3 days before completion of the work, which means last 3 days work is done by Arun
The work done by Arun in last 3 days = 3(1/24) = 1/8
As we know total work will be equal to 1
⇒ = 1
⇒
⇒
⇒
⇒
⇒ 5x = 72 - 44
⇒ 5x = 28
⇒ x = 28/5 = 5 3/5
Therefore, Arun and Bharath worked together for 5 3/5 days
The numbers of days taken to complete the total work = 4 + 5 3/5 + 3
= 12 3/5 days
Therefore,
The number of days taken to complete the total work = 12 3/5 days
#SPJ2