Math, asked by Doragirl, 5 months ago

Asha can complete 1\10
of a work in 3 days. How long will she take to do2\5 of the work?
i. 5 days
ii. 10 days
iii. 12 days
iv. 6 days

Yrr kisi ko pta ho iska ans to please jaldi bta do par full explain karke ​

Answers

Answered by Anonymous
14

Answer:

12 days

Step-by-step explanation:

Asha completes 1/10 of the work in 3 days….

Which means,

1/10 work = 3 days

1 work = 3*10days

1 work = 30 days

she can finish the whole work in 30days.

So 2/5 of the work would be

2/5 work = 2/5 of 30days

2/5 work = 12 days

Hence the answer is 12 days

Hope it's help you ☺️☺️

mark my answer as

brainlist

Answered by hadiyanaveed212
2

Answer:

12 days

Step-by-step explanation:

work:days

1/10:3

2/5:x

x/3=2/5÷1/10

x/3=2/5×10

x/3=2×2

x/3=4

x=4×3

x=12days