@= A contractor estimates that 3 persons could rewire Jasminder's house in 4 days. If,
he uses 4 persons instead of three, how long should they take to complete the job?
Answers
Answered by
9
Answer:
Total work= 3(person)×4(days) = 12
Now number of persons=4
4(persons)× x(days) = 12
x(days) =12÷4= 3 days
This is a case of inverse proportion