B and C can complete a piece of work in 12 days. C and A do it in 8 days and A and B can alone complete it in 8 days. how much time will A alone take to complete the work
Answers
Answered by
3
Answer:
one day work
B+C=1/12
C+A=1/8
A+B=1 / 8
Adding:>2 days work
2A+2B+2C=1/12 +1/8+1/8
=2/24 +3/24 +3/24=8/24=1 / 3
one day work of A,B,C=1 /6
A' will complete the work=
1/6-1/12=6/72 = 1/12
12 days. Ans