Math, asked by pakshipoojar116, 10 months ago

B is 40% less efficient than A and efficiency of C is 1/4 th the efficiency of A and B together. If C joined A and
B every third day then all three together complete the work in 27(3/4) days. Find in how many days will B
alone complete the work?
1.40days
2.60days
3.50days
4.100 days 5.80days​

Answers

Answered by amitnrw
1

B alone will complete in 80 Days

Step-by-step explanation:

Let say A's 1 Day work  =  A

then B's 1 Day work  = A - (40/100)A  = 0.6A

C's 1 Day work  = (A + 0.6A)/4  = 0.4A

C joined A and B every third day then all three together complete the work in 27(3/4) days

=> A & B worked each for 27 3/4  = 111/4  Days

C worked for 9 days  

Total Work done =  A(111/4)  + (0.6A)(111/4)  + 0.4A * 9

= 0.4A * 120

= 48A

B's 1 Day work  = 0.6A

days  B will alone complete the work  = 48A/(0.6A)  =  80 Days

B alone will complete in 80 Days

Learn more:

Ajay along with Vijay do a work in 10 days. If Ajay do a work in 1/2 ...

https://brainly.in/question/10694066

Nitesh does a certain work such that everydays his efficiency falls by ...

https://brainly.in/question/11682428

A and B can complete a work in 30 days and 40 days.respectively. If ...

https://brainly.in/question/10017939

Answered by madhurimachatterjee9
0

Answer:

80days

Step-by-step explanation:

B's 40% less efficient than A

then A:B = 100:60 = 5:3

C's efficiency 1/4 th of (A+B) then efficiency of C = 2

Now every third day C joined for work so C work for 9days (27/3) whereas A & B both work for 27 3/4 days.

So Total Work (eff * Time) = 111/4 * 5 + 111/4 * 3 + 9*2 = 240

then Total Work done by B = 240/3 = 80 days

Similar questions