C, D and E can do a piece of work in in 10 days, 12 days and 15 days respectively. how long will they take to finish it if they work together?
solve it
Answers
Answered by
1
Answer:
1/4
Step-by-step explanation:
C' s 1 day work = 1/10
D's 1day work = 1/12
E's 1 day work = 1/15
in 1 day they together does = 1/10 + 1/12 +1/15
10×12+12×15+15×10
=_____________________
10×12×15
=450/1800
=1/4 hence they can do the work in 4 days