Calculate the earning of workers A and
B under Straight piece-rate system and
Taylor's Differential Piece-rate System
from the following particulars: Normal
rate per hour = Rs. 1.80 Standard time
per unit = 20 seconds Differentials to
be applied: 80% of piece rate below
standard 120% of piece rate at or above
standard. Worker A produces 1,300
units per day and worker B produces
1,500 units per day.