called integers
90. 12 men complete a work in 20 days if only 8 m
are employed, the number of days required to comple
the same work is
1) 24 days 2) 25 days
3) 30 days
4) 35 days
Answers
Answered by
1
Answer:
1) 12/20*a/8
a= 12/20*8
=24/4 days.
Answered by
0
Answer:
12/20*a/8
a= 12/20*8
=24/4 days.
Step-by-step explanation: