1. Ten men started on a job. After some days four men left. So, instead of 40days the job took 50 days
all. After how many days did the men leave?
ays four men left. So, instead of 40 days the job took 50 days i
Answers
Answered by
8
Answer:
25 days
Step-by-step explanation:
target mandays=10*40=400
say after " d" days 4 man left
10d+6(50-d)=400
10d+300-6d=400
4d=100
d=25 days