Math, asked by kavitababubill, 3 months ago

certain number of people are working on constructing the room in 32 days. they worked together for 8 days and then 20% people left. 16 days after 20% people left the job, it was decided to increase the number of people to complete the work on time. find the ratio of number of new people recruited to the original number of people on the job.​

Answers

Answered by subha9935
0

Step-by-step explanation:

Let there be n workers

Work done by each man per day = 1/32n

Amount of work done in 8 days = 8/32 = 1/4

Now workers left = n - 20%n = 4n/5

Work done by 4n/5 workers in 16 days = 4n/5 × 1/32n × 16 = 2/5

total work left = 1 - 1/4 - 2/5 = 7/20

Number of days left = 32-8-16 = 8 days

So work done per day = 7/20 ÷ 8 = 7/160

number of workers required =7/160 ÷ 1/32n = 7n/5

ratio = 7n/5 : n = 7:5