Challenge
50 workers can complete laying the tiles of a mall in 10 days. How many additional workers are required if
after 3 days it is decided that the work must be completed in 8 days instead of 10 days?
(a) 40
(b) 10
(c) 20
(d) 5
Answers
Answered by
3
Answer:
20 worker required to complete the work