Accountancy, asked by mazzambedkar786, 2 months ago

Clear selection

Total cost incurred to date 5,20,000, cost of work certified is 3,50,000 work

uncertified will

200000

170000

350000

270000​

Answers

Answered by AdityaBadone
1

Answer:

1,70,000

Explanation:

Total Cost = Certified Work + Uncertified Work

5,20,000 = 3,50,000 + Uncertified Work

Uncertified Work= 5,20,000 - 3,50,000

Uncertified Work = 1,70,000

Answered by sreyesh3
1

Answer:

170000

Explanation:

uncertified work = total cost - certified work

= 520000 - 350000

= 170000