Clear selection
Total cost incurred to date 5,20,000, cost of work certified is 3,50,000 work
uncertified will
200000
170000
350000
270000
Answers
Answered by
1
Answer:
1,70,000
Explanation:
Total Cost = Certified Work + Uncertified Work
5,20,000 = 3,50,000 + Uncertified Work
Uncertified Work= 5,20,000 - 3,50,000
Uncertified Work = 1,70,000
Answered by
1
Answer:
170000
Explanation:
uncertified work = total cost - certified work
= 520000 - 350000
= 170000
Similar questions