Math, asked by madhusharma38, 10 months ago

cocept of time and work​

Answers

Answered by sweety9379
1

Answer:

The basic concept of Time and Work is similar to that across all Arithmetic topics, i.e. the concept of Proportionality. ... Hence, if A finishes a work in 4 days, it means- in 4 days he will do 100% of the work. Hence, in one day he finishes 25% (100/4) of the work. Similarly, in 3 days he finishes 75 % of the work.

Step-by-step explanation:

Plz mark as brainliest