completion of the work. In how many days will the whole work be completed?
Piyush and Ajit together can complete a work in 3 days. They started together but after 2 days Ajit
work If the work is completed after 2 more days, Piyush alone can complete it in how many days?
Cin 15 dans All of them began the work toget
Answers
Answered by
0
Answer:
Let the total unit of work be 6 units (LCM of 2 and 3)
(A+B)do=
3
6
=2 units/day
(A+B)
′
s2 day work =2×2=4 units
Work left =6−4=2 units
This remaining work is done by A in 2 days.
∴A
′
s per day work =
2
2
=1 unit/day
∴B
′
s per unit work =(A+B)
′
s work−A
′
s work
=2−1=1 unit/day
B alone can complete the work in =
1
6
=6 days.