Construct a network for the following training and development project.
Preceding
Activity TE (weeks) Activities
a: Select personnel 3 none
b: Invite personnel 5 none
c: Budget ok? 14 a
d: Prepare materials 5 a
e: Engage instructor 4 b
f: Select date 7 b
g: Remind personnel 8 d, e
h: Start project 5 g, f
(a) Draw the network.
(b) Find the critical path.
(c) Assume activity a (hire trainers) took 5 weeks. Replan the project.
(d) From where would you suggest transferring resources, and to what activities, so that the original
target training date may be maintained?

Answers

Answered by sonutetarwal516
0

Answer:

I do not know I am on class 10th so sorry please

Answered by Anonymous
0

Answer:

  • hi

Explanation:

ok

good morning dear have nice day byyy