Math, asked by harshbhushan1372, 1 year ago

Creative constructors has hired some workers from bihar. From those newly appointed workers if 10 men working 6 hours a day can do a work in 20 days. Then 8 men working 10 hours a day can do it in how many days?

Answers

Answered by Haridasan
0

requires 15 days. This is the ans.