Cycle Time can be shortened for an Assembly Line using _____worstations
Select one
a Virtual
b. Real
c. Parallel
d. Sequential
Answers
Cycle Time can be shortened for an Assembly Line using _ PARALLEL _ workstations
Explanation:
virtual workstation is not related to assembly line:
A virtual workstation is a cloud-based workstation .
In Assembly line every workstation is real workstation only
Sequential Work station will have Cycle time dependent upon Critical Task
in Parallel Work Stations , Cycle time for critical task can be reduced by doing that task in parallel and
Hence Cycle time can be reduced
Cycle Time can be shortened for an Assembly Line using _Parallel_ workstations
Eg. Task A - 2 minutes , Task B - 4 minutes Task C 2 minutes
Cycle time = 4 minutes
Now Task B is Paralleled then We will get twice in 4 minutes Hence
New cycle time = 2 minutes
Learn More:
Minimum inventory is to ensure :O A minimum working capitalO B ...
https://brainly.in/question/31819881
Answer:
virtual workstations is the answer pls mark as brainliest