Math, asked by Raveena7, 1 year ago

David can pack 132 cartons of jar in one day and his assistant Mark works one quarter as fast as david does. How many days would it take both of them working together to pack 660 cartons?
show calculation


premkumar2: 4 days
Raveena7: please show calculation.. i need it

Answers

Answered by premkumar2
1
4 days is needed to pack 660 cart
Attachments:

Raveena7: image is blur :(
Raveena7: got it.. thankyouu :)
premkumar2: Mark it as best
Answered by AL2006
1
David can pack 132 cartons of jar in one day and his assistant Mark works one quarter ( 1/4)  as fast as David does.

David produces 132 cartoons in 1 day

Mark produces 1/4 of 132 = 33 cartoons in a day 

They both produces (132+33) = 165 cartoons in a day. 

To produce 660 cartoons, it will take: 
 

660 ÷ 165 = 4 days
Similar questions