Math, asked by chettriashish752, 2 months ago

Deepak can a complete a work in 12 days and Deepak and krishna can complete in 8 days .what fraction of work can krishna complete in one days​

Answers

Answered by Anonymous
0

Answer:

yur answer will be 3 by 2 for one day work

Step-by-step explanation:

Hope it helps you

Answered by AneesKakar
0

Answer:

work done by Krishna in one day is 1/24.

Given:

Deepak can complete a work in 12 days

Deepak and Krishna can complete in 8 days

To find:

the fraction of work that Krishna can complete in one day

Solution:

total work done by Deepak in one day= 1/12

total work done by Deepak and Krishna together= 1/8

total work done by Krishna in one day= 1/24

total work done in 1 day = work done by Krishna in 1 day + work done by Deepak in 1 day

1/8 = 1/x + 1/12

1/8 - 1/12 = 1/x

2/48 = 1/x

1/24 = 1/x

total time taken by Krishna to complete the work= 24

work done by Krishna in one day= 1/24

Hence, 1/24 is the correct answer.

#SPJ2