Math, asked by pradeepgiri833, 11 months ago

Deepak can do a work in 18 days he works alone for 6 days and Mohit alone finish the remaining work in 24 days both of them working together can complete in the same work in how many days​

Answers

Answered by bhagyashreechowdhury
1

If both Deepak and Mohit are working together then they can complete the same work in 12 days.

Step-by-step explanation:

Deepak alone can do a piece of work in 18 days

So, work done by Deepak in 1 day = \frac{1}{18}

He works alone for 6 days

So, work done by Deepak alone for 6 days = \frac{6}{18} = \frac{1}{3}

The remaining amount of work to be done will be = 1 – \frac{1}{3} = \frac{2}{3} this amount is done by Mohit alone in 24 days.

Mohit alone can do a piece of work in = 24 * (\frac{3}{2} ) = 36 days

So, work done by Mohit in 1-day will be = \frac{1}{36}

Therefore,

The work to be done, if both Deepak and Mohit works together to complete the same work, will be given by,

= \frac{1}{18}  + \frac{1}{36}  

= \frac{2+1}{36}

= \frac{3}{36}

= \frac{1}{12}

Thus, the same amount of work is completed in 12 days if both Deepak and Mohit works together.

----------------------------------------------------------------------------------------

Also View:

A can do a piece of work in 4 days. b can do it in 5 days. with the assistance of c they completed the work in 2 days. find in how many days can c alone do it?

https://brainly.in/question/5201607

Ajsy can do 3/4 th of a,work in 6 days and vijay can do 2/5 of the same work in 4 days. Find the no. Of days in which both.ajay and vijay together can complete the work ?

https://brainly.in/question/7553769

Similar questions