Difference between cpm and pert in project management
Answers
Answered by
0
Answer:
PERT is event oriented whereas CPM is activity oriented. In simple words, in PERT network interest is focused upon start or completion of events and not on activities themselves. 2. In CPM network no allowance is made for uncertainties in the duration of time involved whereas in PERT network uncertainty is considered
Explanation: