Difference between product oriented deliverables and project oriented deliverables ques10

Answers

Answered by SREEBHARATH
0
After the project scope is defined, the next step is to define the activities or tasks the project team must undertake ore fulfil the scope deliverable requirements. The work breakdown structure is a useful tool for developing the project plan and links the project’s scope to the schedule and budget.

The WBS represents a logical decomposition of the work to be performed and focuses on how the product, service, or result is naturally subdivided. It is an outline of what work is to be performed.

The WBS provides a framework for developing a tactical plan to structure the project work. The WBS is a hierarchical decomposition of the project’s scope that the project team will deliver over the course of the project. The total scope of the project is divided and subdivided into specific deliverables that can be more easily managed. The WBS provides an outline for all of the work that that project team will perform.

Similar questions