Efficiency of a single movable pulley is 0.8. When an effort of 100N goes up by 2 metre then a load of_N goes _ by 1 meter
Answers
Answered by
0
Answer:
Load L is attached to the movable pulley. A rope is fi xed at a point in ceiling that passes through the moveable pulley.
In order to lift the effort E by x meters, the load L needs to
Travel the distance of x/2 meters. (The entire rope needs to be pulled by E for a distance of x)
Now, Velocity Ratio equals (Distance traveled by E) divided by (Distance traveled by L)
So it becomes : x/(x/2). This equals to 2
Since it is a ratio. it has no units of measurement.