Math, asked by gothadiyamanishah, 4 months ago

Efficiency of Kanchan is four times to that of
Hina. If they will complete the work is 24
days by working together, then in how many
days can Hina alone complete the work ?
(a) 36 days
(b) 24 days
(c) 144 days
(d) 96 days​

Answers

Answered by praveenprithy07
1

Answer:

Hina can complete the work in 120 days which is not in the given option.

Step-by-step explanation:

We have given efficiency of Kanchan is 4 times as that of Hina

Let the work done by Hina in one day is 1

Then work done by Kanchan in 1 day = 4

So total work done by both in one day = 4+1 = 5 work

As they can together complete the work in 24 days

So total work = 24×5 = 120 work

As in one day Hina does 1 work

So time taken by Hina to complete 120 work  = 120 days

Learn more

A and B together can complete a job in 35 days. While A alone can complete it in 60 days. B

alone can complete the job in:

(a) 42 days

(b) 96 days

(c) 72 days

(d) 84 days.

Answered by mayankkumarmk1212
26

Question:-

  • Efficiency of Kanchan is four times to that of Hina. If they will complete the work is 24 days by working together, then in how many days can Hina alone complete the work ?
  1. (a) 36 days
  2. (b) 24 days
  3. (c) 144 days
  4. (d) 96 days​

To find:-

  • Number of days hina will take to complete the work alone.

Solution:-

We have given efficiency of Kanchan is 4 times as that of Hina

Let the work done by Hina in one day is 1

Then work done by Kanchan in 1 day = 4

So total work done by both in one day = 4+1 = 5 work

As they can together complete the work in 24 days

So total work = 24×5 = 120 work

As in one day Hina does 1 work

So time taken by Hina to complete 120 work  = 120/1 = 120 days

Answer:-

  • Hina can complete the work in 120 days which is not in the given option.

I hope it helps...