Math, asked by saradevi19, 8 months ago

Eight men and twelve boys can finish a piece of work in 10 days while six man and eight boys can finish the same work in 14 days. Find the number of days taken by one man alone to complete the work and also one boy alone to complete the work.​

Answers

Answered by baski3d
0

Answer:

Yes! Here is your answer!

Step-by-step explanation:

Let the time taken by man be x days

time taken by boys be y days

work done by 1 man in one day=1/x

work done by 1 boy in one day=1/y

8/x+12/y = 1/10............eq 1

6/x+ 8/y = 1/14..........eq2

Let u=1/x & v=1/y

8u+ 12y=1/10.........eq3

6u+8v= 1/14...........eq4

Multiplying eq3 by 2 & eq4 by 3

16u+ 24y=2/10.........eq5

18u+24v= 3/14.........eq6

subtract eq 5 & 6

-2u= -3/14+2/10

-2u = (-3×10 +2×14)/140

-2u=( -30+28)/140

-2u=-2/140

u=1/140

put this value in eq 5

16u+ 24y=2/10

16×1/140 +24y =1/5

4/35+24y= 1/5

24y= 1/5-4/35

24y= (1×7 -4)/35

24y = (7-4)/35

24y= 3/35

y= 3/35×24

y= 1/280

u=1/x

1/140 = 1/x

x=140

v=1/y

1/280 = 1/y

y=280

A man complete the work in 140 days

A boy can complete the work in 280 days