Ex 7: If 30 men working 7 hrs a day can do a piece of work in 18 days, in
how many days will 21 men working 8 hrs a day do the same piece
of work?
Answers
Answered by
1
Step-by-step explanation:
for these problems follow the formulae ((M1)*(D1)*(H1))/(W1)= ((M2)*(D2)*(H2))/(W2)
WHERE M- men or women
H- hours
D-days
W- work
here work is same .therefore W1=W2
M1*D1*H1=M2*D2*H2
30*7*18=21*8*x
implies X=22.5 days