Example 19:
Eight men can dig a field in 14 days, working 6 hours a day. In how many days can
7 men dig the same field, working 8 hours a day?
Answers
Answered by
15
Here is your answer:
Attachments:
Answered by
0
Answer:
7 men working for 8 hours each would take 12 days to finish the same job
Step-by-step explanation:
given, 8 men working 6 hours a day can dig the field in 14 days
to find: number of days required to dig the same field by 7 men working 8 hours a day
let x be the number of days required by 7 men, working 8 hours a day, to dig the field
number of men 8 7
number of working hours 6 8
number of days required 14 x
then, a1×b1×c1 = a2×b2×c2
⇒ 8 × 6 × 14 = 7 × 8 × (x)
⇒ 672 = 56x
⇒ x = = 12
thus, 7 men working for 8 hours each would take 12 days to complete the same job
Similar questions
Science,
5 months ago
English,
5 months ago
Math,
11 months ago
Social Sciences,
1 year ago
Chemistry,
1 year ago