explain and compare various types of floats as used in network analysis.
Answers
Answered by
1
Answer:
can i say u about it but u have to follow me pls
Answered by
5
Answer:
Free float is the amount of time that a task can be delayed without impacting the subsequent task.
Total float is the amount of time a task or a project can be delayed without impacting the overall project completion time.
Float is a key piece of the critical path method (CPM), a system used by project managers to efficiently schedule project activities.