Fabric X has to go through three stages of manufacturing, viz., spinning, weaving and dyeing. In Rimal Fabric Company, there are six spinning machines, ten weaving machines and five dyeing machines. Each machine works for 10 hrs a day. One unit of Fabric X needs 40 minutes on a spinning machine, 2 hours on a weaving machine and 30 minutes on a dyeing machine in order to be completed. Similarly one unit of Fabric Y needs 60 minutes on a spinning machine, 30 minutes on a weaving machine and 60 minutes on a dyeing machine in order to be completed.
yeh table explain kardo plzzz
Answers
Answer:
Step-by-step explanation:
Fabric X has to go through three stages of manufacturing, viz., spinning, weaving and dyeing. In Rimal Fabric Company, there are six spinning machines, ten weaving machines and five dyeing machines. Each machine works for 10 hrs a day. One unit of Fabric X needs 40 minutes on a spinning machine, 2 hours on a weaving machine and 30 minutes on a dyeing machine in order to be completed. Similarly one unit of Fabric Y needs 60 minutes on a spinning machine, 30 minutes on a weaving machine and 60 minutes on a dyeing machine in order to be completed.
yeh table explain kardo plzzz
Table has below data
X 0.66 hr 2 hr 0.5 hr time required per unit processed
Y 1 hr 0.5 hr 1 hr time required per unit processed
Spinning Weaving Dyeing
C 60 100 50 Capacity Available
X needs 40 minutes on a spinning machine = (40/60) = 2/3 = 0.66 hr
X need 2 hours on a weaving machine = 2 hr
X need 30 Mins on a dyeing machine = 30/60 = 1/2 = 0.5 hr
Y needs 60 minutes on a spinning machine = (60/60) = 1 hr
Y need 30 hours on a weaving machine = 30/60 = 1/2 = 0.5 hr
Y need 60 Mins on a dyeing machine = (60/60) = 1 hr
Capacity per day = Number of opertaion output per day = Number of Machines * No of hrs / (time require per unit processed)
No of Hrs = 10 hrs each
Spinning Machines vailable = 6
Capacity of X for Spinning = (6 * 10) /0.66 = 90
Capacity of Y for Spinning = (6 * 10) /1 = 60
Weaving Machines vailable = 10
Capacity of X for Weaving = (10 * 10) /2 = 50
Capacity of Y for Weaving = (10 * 10) /0.5 = 200
Dyeing Machines vailable = 5
Capacity of X for Weaving = (5 * 10) /0.5 = 100
Capacity of Y for Weaving = (5 * 10) /1 = 50