Fifteen men can build a wall in 60 days.How many more men are required to build another wall of same size in 45 days.
Answers
Answered by
0
It is inverse data
So....
So....
Attachments:
rahulsda864p5czp7:
no answer is wrong
Answered by
9
Number of men - 15
Number of days- 60
Number of the other days-45
Then,
No. of men-15*60/45
Then the answer will be 20 men
Hope, this helps...
Number of days- 60
Number of the other days-45
Then,
No. of men-15*60/45
Then the answer will be 20 men
Hope, this helps...