Given
Lenght of the cuboidal = 8m
Breath of the cuboidal = 6m
Height of the cuboidal = 3m
Formula-:
Now-:
On putting the required values
We get,
Now-:
As given the rate of digging is
1 m cube = 30 /-
144 m cube = 30 x 144
= 4320/-
Therefore-:
Total cost will be rupees 4320.
Answered by
23
Answer:
volume of cubiod = l×b×h
volume. =8m×6m×3m
volume =144m^3
rate of 1 m^3 = ₹30
for 144m^3 cost will be = 144×30 = ₹4320
Total cost will be ₹ 4320