find the cost of digging a cuboidal pit 8 metre long 6 metre board and 3 metre deep @ rupees 30 per metre cube
Answers
Answered by
2
Answer:
Rs 4320/-
Step-by-step explanation:
given
l=8m
b=6m
h=3m
volume of cuboid =8*3*6
=144m*m*m.
the cost for @ 30 rupees =144*30
=4320/-
therefore the cost of digging is 4320/-.
Answered by
1
Cost of digging the pit = Rs. 4320
Step-by-step explanation:
Given: Cuboid pit that is 8m long, 6m broad and 3m deep @ Rs. 30 per m³.
Volume of the pit = length × breadth × height
= 8 * 6 * 3
= 144 m³.
Cost of 1 m³ = Rs. 30
Cost of digging 144 m³ = 144 * 30 = Rs. 4320