five workers take 18 days to weed a field. how many days would 9 workers take
Answers
Answered by
2
Step-by-step explanation:
Suppose 9 workers take x days.
So No. of workers increase, No. of days decrease.
No. of days and workers are in inverse proportion.
∴ 5 × 18 = 9 × x
⇒ x = 90/9
x = 10 days
Therefore, 9 workers will take 10 days to weed a field.
MAY THE ANSWER HELPS YOU :)
Answered by
0
Answer:
5×18=9×x
x=90\9
x=10 days
Therefore 9 ,worker will take 10 days to weed a field.